Feb 19, 2025 Leave a message

The Operating Procedures Of The Shot Blasting Machine Must Be Strictly Followed

1. Strictly follow the fixed personnel and job training to operate the equipment, and be familiar with the performance and characteristics of the machine.
2. Familiar with the operating procedures, usage, maintenance, and upkeep of the shot blasting machine in the user manual.
3. The operator must check whether all types of switches in the control cabinet (panel) are in the required set positions (including all power switches) before starting up, in order to avoid misoperation, damage to electrical and mechanical equipment, and equipment accidents.
4. Non local operators are not allowed to operate or touch the electrical switch control area at will, and are not allowed to approach the local work area to avoid accidents.
5. Operators must wear protective work clothes, glasses, etc.
6. The operator should pay special attention to the various instrument indications on the panel when turning on the machine. Only when all instrument indications reach normal values can the small crane (roller conveyor) be operated into the working program. If significant errors (abnormal) are found in individual instrument readings, immediately shut down. Only after troubleshooting the equipment can it start working normally.
7. During the operation of the equipment, the operator must inspect and check whether there are any abnormal noises or overheating phenomena in various parts of the equipment. When serious equipment malfunctions are found during operation, press the "emergency stop" button to stop the machine for repair, and cooperate with professional personnel to troubleshoot the equipment.
8. The operator must perform daily and weekly maintenance (including lubrication) on this equipment according to "equipment management". Clean the dust and debris in the dust collector in a timely manner every week to avoid affecting the quality of dust removal and ensure the integrity of the equipment.
9. Operators must ensure civilized and safe production while strictly implementing the shift handover system.
10. At the end of the work, immediately cut off the power switch of this machine to prevent it from running. And clean up the work site.

Send Inquiry